New Central Fire Station Drawing as of 8-5-09
Architect:
Short Elliot Hendrickson Inc. (SEH)
Construction Manager: Oscar J. Boldt Construction
Fire Station Time Line as of 10-6-09
Note: All dates listed are start dates and subject to change
| Bids for Demolition, Asbestos, PreCast Exterior Panels &
Bi-Fold Doors due Bid Package #1 |
June 22, 2009 |
| Demolition Begins |
August 5, 2009 |
| Bids for all other construction components Bid Package #2 due |
September 3, 2009 |
| Fabricate Exterior PreCast Panels |
September 28, 2009 |
| Ground Breaking |
September 30, 2009 |
| Pour and form footings/foundations |
October 9, 2009 |
| Erection of PreCast Exterior Panels |
December 7, 2009 |
| Install Roofing |
January 15, 2010 |
| Install office interior finishes |
March 24, 2010 |
| Pour and form site concrete |
April 15, 2010 |
| Pave and landscape |
May 3, 2010 |
| Substantial completion |
August 22, 2010 |
Subcontractors
| Construction Category |
Subcontractor |
| Precast Panels |
Wells Concrete |
| Bi-Fold Doors |
JF Cook |
| Concrete Foundation and Slab on Grade |
Altmann Construction |
| Masonry |
Selmer |
| Structural and Misc. Steel |
Daigle Brothers |
| Rough and Finish Carpentry |
Altmann Construction |
| Roofing |
Quality Roofing |
| Aluminum Entrances and Windows and Glazing |
Esser Glass |
| Metal Studs and Drywall |
Decker Lumber |
| Tile |
Grazzini Brothers |
| Acoustical Ceiling |
Appletyon Lathing |
| Flooring |
Gegare Tile |
| Painting |
Decker Lumber |
| Manufactured Casework |
Wynn O. Jones |
| Elevator |
Schindler |
| Fire Protection |
Integrity Fire Protection |
| Plumbing |
August Winter |
| Mechanical |
B & P Mechanical |
| Electrical |
Dakota Electric |
| Excavation and Site Grading |
Nikolay Transport |
| Asphalt |
American Asphalt |
| Curb and Gutter |
Martell Construction |
| Site Concrete |
Martell Construction |
| Fence |
American Fence |
| Landscaping |
Carl's Landscaping |
| Site Utilities |
August Winter |
Fire Station Location
View with Building Footprints
View with Aerial Photo
Aerial
View with representation of new station on the Proposed Site
Note" These drawings are not to scale and are only
intended as a representation

Exterior Elevations - Click on picture for larger view

First Floor Layout - Click on picture for larger view
(Note: page 2 of 6)

Second Floor Layout - Click on picture for larger
(Note: Page 3 of 6) view
Site Layout - Click on picture for larger view (Note: Page 1 of
6)

Construction Pictures

Energy Efficiencies
Designed into this LEED Silver Facility
Back to FD Home Page

|