New Central Fire Station Drawing as of 8-5-09

                                                                                                 Architect:                             Short Elliot Hendrickson Inc. (SEH)

                                                                                                Construction Manager:        Oscar J. Boldt Construction

 

                                                 Fire Station Time Line as of 10-6-09

                                                                                                            Note:  All dates listed are start dates and subject to change

 Bids for Demolition, Asbestos, PreCast Exterior Panels &   Bi-Fold Doors due Bid Package #1 June 22, 2009
Demolition Begins August 5, 2009
Bids for all other construction components Bid Package #2 due September 3, 2009
Fabricate Exterior PreCast Panels September 28, 2009
Ground Breaking September 30, 2009 
Pour and form footings/foundations October 9, 2009
Erection of PreCast Exterior Panels December 7, 2009
Install Roofing January 15, 2010
Install office interior finishes March 24, 2010
Pour and form site concrete April 15, 2010
Pave and landscape May 3, 2010
Substantial completion August 22, 2010

 

 

 

 

 

 

 

 

 

 

 

                                                                                        

 

                                                                                                                         Subcontractors

 

 

Construction Category Subcontractor
Precast Panels Wells Concrete
Bi-Fold Doors JF Cook
Concrete Foundation and Slab on Grade Altmann Construction
Masonry Selmer
Structural and Misc. Steel Daigle Brothers
Rough and Finish Carpentry Altmann Construction
Roofing Quality Roofing
Aluminum Entrances and Windows and Glazing Esser Glass
Metal Studs and Drywall Decker Lumber
Tile Grazzini Brothers
Acoustical Ceiling Appletyon Lathing
Flooring Gegare Tile
Painting Decker Lumber
Manufactured Casework Wynn O. Jones
Elevator Schindler
Fire Protection Integrity Fire Protection
Plumbing August Winter
Mechanical B & P Mechanical
Electrical Dakota Electric
Excavation and Site Grading Nikolay Transport
Asphalt American Asphalt
Curb and Gutter Martell Construction
Site Concrete Martell Construction
Fence American Fence
Landscaping Carl's Landscaping
Site Utilities August Winter

 

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Fire Station Location

                                                                                                                                                                           

                                                                                           View with Building Footprints                                View with Aerial Photo                     

 

                                                                                                       Aerial View with representation of new station on the Proposed Site

     Note"  These drawings are not to scale and are only intended as a representation

 

                                                                                                                 

                                                                            

                                                                                                                   Exterior Elevations - Click on picture for larger view

                                                                                     

                                                                                                        First Floor Layout - Click on picture for larger view (Note: page 2 of 6)

 

                                                                                     

                                                                                                            Second Floor Layout - Click on picture for larger (Note: Page 3 of 6) view                                          

                      

                                                                                              

                                                                                                         Site Layout - Click on picture for larger view   (Note: Page 1 of 6)

 

                                                                                                   

                                                                                                                                                   Construction Pictures

 

                                                   

                                                                                                                                      

                                                         Energy Efficiencies Designed into this LEED Silver Facility

 

 

 

 

 Back to FD Home Page